| The plan
to replace the field
After assessing the safety and recreational needs
of children as well as the large number of community members and
neighborhood sports groups who use the field, the district planned
to replace the field in Phase II of the district's 20-year construction
plan. Voters approved that phase of the plan in 1998. To do the
job right, replacement of the field would have to involve more than
just replacing sod or laying new seed to grow grass. After time,
the field would again be unsafe.
The plan called for removal of the old turf and exposed
ground, shoveling down a few feet to allow a recommended layer of
gravel and sand to be placed underneath, which would allow water
to drain properly through the new turf, into the ground and away
from the topsoil. (A process recommended to help prolong the life
of the field and keeping water from standing on top of the ground
causing excessive damage.) The plan also called for placement of
an irrigation system to water the field in the summer months which
would also help to prolong the life of the field. Proper drainage
allows the field to be used year-round, not only by students at
the school, but also by community groups, local soccer and baseball
clubs and the general public.
Discoveries that caused delays
The plan to replace the field was on time when, in
August, contractors unearthed parts of past school buildings that
had been demolished and covered up. Foundations and fragments of
basements from both the 1940 and 1913 school buildings were found
just a few feet under the surface of the field. The 1913 foundation
was demolished and removed; however, the foundation from the school
built in 1940 had concrete reinforced with rebar (steel bars placed
in concrete to strengthen foundations) which meant removal would
prove too extensive and costly. The field would have to be constructed
with the old foundation in place. To accomplish that, engineers
had to resurvey the field and create a new set of plans. The new
plans were drawn and the process to remove old soil and place compacted
layers of rock and sand soon began. By this time, unusually early
and heavy fall rains began which saturated the layer of sand, slowing,
sometimes halting the process.
Project remains on time and within budget
Progress is quickening. Most of the irrigation system
is in place. The final layers of underlayment (rock and sand) are
likewise being laid to allow topsoil to be brought in and seed to
be planted by February. The project is still within the original
budget and timeline. The field is scheduled to be ready for student
and community use by September. As in the original plan, fencing
will remain around the turf portion of the field through the summer
and into early fall to allow grass to grow in properly.
Phase III of the district's 20-year construction plan
is on the February 5 ballot, currently before Renton voters. That
plan includes rebuilding Kennydale Elementary School. If the bond
passes, the new school will be built on site without disruption
to the new field. Trees removed due to rotting roots and falling
debris during the field replacement project will be replaced with
a new variety of trees and other landscaping. |